2026-09-28: Make financing timelines full width
Financing Timeline Carousel
Section titled “Financing Timeline Carousel”Make the Cash, Custom Down Payment, and Full Financing timelines easier to inspect by giving each timeline the full available content width and letting users scroll horizontally between them.
Design
Section titled “Design”- Replace the three-column timeline grid with a horizontally scrollable row of full-width timeline cards.
- Use scroll snapping and an accessible, keyboard-focusable region to navigate between the three timelines.
- Preserve the existing comparison summary cards and table-level scrolling behavior.
Verification
Section titled “Verification”- Frontend unit coverage verifies the labelled scroll region and all three timelines.
- Playwright coverage verifies horizontal navigation between timeline cards without causing page-level horizontal overflow.
- Run frontend unit and e2e suites and the docs build.
Constraints
Section titled “Constraints”- No backend, API, or data model changes.
- The worktree contains unrelated uncommitted changes; keep this change limited to the financing comparison UI, its tests, and docs.
Execution Summary
Section titled “Execution Summary”Actual changes
Section titled “Actual changes”- Replaced the three-column timeline grid with full-width, horizontally scrollable cards. The labelled scroll area supports keyboard focus and snap navigation; summary cards and table scrolling remain unchanged.
- Added frontend unit and Playwright coverage and documented how to move between the timelines.
Deviations
Section titled “Deviations”- Playwright’s managed Chromium executable was unavailable. The full browser suite ran with installed system Chrome using a temporary config in
/private/tmp; no browser path or config was added to the repository. - No product or implementation decisions changed from the approved plan.
Test results
Section titled “Test results”- Backend unit: 35 suites, 348 tests passed; 97.33% statements and 97.91% lines.
- Backend e2e: 9 suites, 73 tests passed.
- Frontend unit: 74 files, 465 tests passed; 95.03% statements/lines and 91.45% functions.
- Frontend e2e: 13 passed, 22 skipped because the backend API was not running; both financing scenario tests passed.
- Frontend build and docs build passed; the docs build generated 108 pages. The build reported the existing
/404route priority warning.
Commit and release
Section titled “Commit and release”- Commit SHA: none; the changes remain uncommitted. The repository’s
.gitdirectory is read-only in this environment, and the worktree contains unrelated changes that must remain untouched. - The latest tag is
v1.4.0; this bug fix would use patch versionv1.4.1. No release tag or release notes were created because Git metadata is read-only and a release from the current dirty worktree could include unrelated work.
Key discoveries
Section titled “Key discoveries”- The repository did not have Playwright’s pinned browser installed, but system Chrome was available and supported the full e2e run.