2026-09-29: Stack financing timelines
Stack Financing Timelines
Section titled “Stack Financing Timelines”Make the Cash Financing, Custom Down Payment Financing, and Full Financing timelines easier to inspect by displaying each as a full-width card, one after another vertically.
Design
Section titled “Design”- Replace the horizontal snap-scrolling timeline region with a vertical stack of full-width timeline cards.
- Preserve the existing option order, comparison summary cards, card contents, and table-level horizontal scrolling.
- Keep timeline layout changes confined to the frontend; no API or data model changes.
Verification
Section titled “Verification”- Frontend unit coverage verifies all three timeline cards render in order and no horizontal carousel region remains.
- Playwright coverage verifies the cards stack vertically, can be reached through page scrolling, and do not cause page-level horizontal overflow.
- Run backend unit and e2e, frontend unit and e2e, and the docs build.
Constraints
Section titled “Constraints”- Leave unrelated worktree changes untouched.
- The existing carousel plan records the previous implementation; this plan records its replacement.
Execution Summary
Section titled “Execution Summary”Actual changes
Section titled “Actual changes”- Replaced the horizontal timeline carousel with three full-width cards stacked vertically in financing option order.
- Updated component and browser coverage for vertical ordering, scrolling, and the absence of page-level horizontal overflow. Updated the financing feature docs.
Deviations
Section titled “Deviations”- Playwright’s pinned Chromium was unavailable. The full browser suite ran with system Chrome and a temporary config outside the repository.
- The complete frontend e2e suite did not pass in this worktree. Financing scenarios passed separately; unrelated asset, dashboard, categories, and tags checks failed, and two tests did not run.
Test results
Section titled “Test results”- Backend unit: 35 suites, 348 tests passed; 97.33% statements and 97.91% lines.
- Backend e2e: 9 suites, 73 tests passed.
- Frontend unit: passed with configured coverage thresholds met.
- Financing frontend e2e: 2 passed. Full frontend e2e: 26 passed, 7 failed, 2 did not run; failures were outside the financing scenarios.
- Docs build: 109 pages built. The existing
/404route priority warning remains.
Commit and release
Section titled “Commit and release”- Commit SHA: none; this work remains uncommitted.
- Latest tag checked:
v1.4.0. Nov1.4.1release was created; the worktree contains unrelated uncommitted changes and Git metadata is read-only in this environment.
Key discoveries
Section titled “Key discoveries”- The full frontend browser run reports unrelated page-level failures in the current worktree. The financing scenario flow and its new stacked-layout assertions pass in isolation.